You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup: - The setup uses a Lean schedule group with a…

The correct answer is B. Create a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 1. Create a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 1. This setup will match the throughput ratio of the Lean setup, which is 2. Since the Lean process activity has a runtime of 3 minutes per quantity, the Discrete operation should have…

Implement production methods

Question

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup:

  • The setup uses a Lean schedule group with a throughput ratio = 2.
  • The process activity tied to production flow has the following runtime activity times: time = 3 min,

per quantity = 1.

  • The work cell capacity has a model type of Throughput and an average throughput quantity of

60 per a capacity period of standard workday (8 hour day).

  • The throughput is 10 per hour.

You need to set up a Discrete operation to mirror the item’s production flow activity. What should you do?

Options

  • ACreate a route with a runtime = 1, a process quantity = 10, and the operation's hours/time = 1.
  • BCreate a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 1.
  • CCreate a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 0.0167
  • DCreate a route with a runtime = 1, a process quantity = 1, and the operation's hours/time = 1.

How the community answered

(36 responses)
  • A
    11% (4)
  • B
    81% (29)
  • C
    3% (1)
  • D
    6% (2)

Explanation

Create a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 1. This setup will match the throughput ratio of the Lean setup, which is 2. Since the Lean process activity has a runtime of 3 minutes per quantity, the Discrete operation should have twice the runtime, or 6 minutes per quantity. The process quantity and operation's hours/time are set to 1 to match the per quantity and time values of the Lean process activity. https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean-

Topics

#Lean manufacturing#discrete manufacturing#throughput calculation#route operations