MB-335 · Question #125
A company uses engineering change management for process manufacturing operations. The company discovers that several products were configured with missing master data during the life cycle of the…
The correct answer is A. standard, non-engineering products D. engineering products E. product versions. You can create readiness checks for new engineering products, variants, and versions. ou can also apply readiness checks to standard (non-engineering) products. https://learn.microsoft.com/en-us/dynamics365/supply-chain/engineering-change- management/product-readiness
Question
A company uses engineering change management for process manufacturing operations. The company discovers that several products were configured with missing master data during the life cycle of the products. You need to configure master data checks for the products. Which three objects can you configure for data checks? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.
Options
- Astandard, non-engineering products
- Bproduct formulas
- Cproduct BOM lines
- Dengineering products
- Eproduct versions
How the community answered
(24 responses)- A75% (18)
- B8% (2)
- C17% (4)
Explanation
You can create readiness checks for new engineering products, variants, and versions. ou can also apply readiness checks to standard (non-engineering) products. https://learn.microsoft.com/en-us/dynamics365/supply-chain/engineering-change- management/product-readiness