MB-335 · Question #109

A manufacturing company is implementing production in Dynamics 365 Supply Chain Management. The production scheduler requires that machines not be scheduled to run concurrently when planning…

The correct answer is A. bottleneck resource B. finite capacity D. job scheduling. You've hit your limit · resets 4am (America/New_York)

Configure production control

Question

A manufacturing company is implementing production in Dynamics 365 Supply Chain Management. The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view. You need to configure the system to meet the requirements. Which three options should you configure? Each answer presents a partial solution. NOTE: Each correct selection is worth one point.

Options

  • Abottleneck resource
  • Bfinite capacity
  • Coperations scheduling
  • Djob scheduling
  • ECapable to Promise

How the community answered

(70 responses)
  • A
    66% (46)
  • C
    11% (8)
  • E
    23% (16)

Explanation

You've hit your limit · resets 4am (America/New_York)

Topics

#job scheduling#finite capacity#bottleneck resource#graphical scheduling