A company configures master planning to order large and expensive aluminum sheets that are only available at certain times of the year. The warehouse manager reports that replenishment levels are…

The correct answer is A. Per period. The Period coverage code is often used for non-predictable inventory draw, season-influenced products, or high-cost products. https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/replenishment-methods-quantity-modification

Configure production control

Question

A company configures master planning to order large and expensive aluminum sheets that are only available at certain times of the year. The warehouse manager reports that replenishment levels are too high, causing inventory value to be over budget. In addition, the aluminum sheets take up too much space on the shop floor. You need to configure the appropriate replenishment method. Which coverage dimension should you use?

Options

  • APer period
  • BManual
  • CMin/Max
  • DPer requirement

How the community answered

(39 responses)
  • A
    72% (28)
  • B
    15% (6)
  • C
    5% (2)
  • D
    8% (3)

Explanation

The Period coverage code is often used for non-predictable inventory draw, season-influenced products, or high-cost products. https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/replenishment-methods-quantity-modification

Topics

#master planning#coverage dimension#per period coverage#replenishment