MB-330 · Question #446
A Canadian company uses Dynamics 365 Supply Chain Management. The company sources a single item from two European vendors. The purchase price agreements are different for each vendor. The shipping…
The correct answer is C. Journey template. Create a cost estimate Use the Cost estimate dialog box to generate a new cost estimate that is based on a selected cost template, a selected set of items, and other details of a journey. These settings are then used to determine the estimated landed costs of goods. These cost…
Question
Exhibit
Options
- AInventory model group
- BVessel
- CJourney template
- DVoyage
How the community answered
(29 responses)- A14% (4)
- B10% (3)
- C72% (21)
- D3% (1)
Explanation
Create a cost estimate Use the Cost estimate dialog box to generate a new cost estimate that is based on a selected cost template, a selected set of items, and other details of a journey. These settings are then used to determine the estimated landed costs of goods. These cost estimates are primarily used to work with standard cost items. By adding the estimated landed costs to the standard cost of goods in inventory, you should experience smaller variance transactions when the goods are added to a voyage, because the standard cost will reflect the estimates of those landed costs. Settings on the Parameters tab The following table describes the fields that are available on the Parameters tab of the Cost estimate dialog box. * Journey template Select a journey template. This field is used to determine the correct auto costs that should be https://learn.microsoft.com/en-us/dynamics365/supply-chain/landed-cost/estimate-manage-