A company uses Dynamics 365 Supply Chain Management. Three assets at a single location all need the same tune-up. A single worker can complete all three tune-ups. The worker's hours must be…
The correct answer is D. Create one work order and split hours by work order job. Create three separate work orders Create one work order and split hours by work order job Configure a job card for the device Configure labor standards Configure the operations resource and set it to human resourc Configure work line details Create a consumption registration…
Implement asset management
Question
A company uses Dynamics 365 Supply Chain Management. Three assets at a single location all need the same tune-up. A single worker can complete all three tune-ups. The worker's hours must be allocated to each asset. You need to configure the system for the worker. Which configuration should you use?
Options
- AConfigure the operations resource and set it to human resource.
- BConfigure work line details.
- CCreate a consumption registration for the expenses.
- DCreate one work order and split hours by work order job.
How the community answered
(52 responses)- A2% (1)
- B6% (3)
- C4% (2)
- D88% (46)
Explanation
- Create three separate work orders * Create one work order and split hours by work order job * Configure a job card for the device * Configure labor standards * Configure the operations resource and set it to human resourc * Configure work line details * Create a consumption registration for the items * Create a consumption registration for the expenses.
Topics
#work orders#work order jobs#labor allocation#hour splitting