Drag and Drop Question A manufacturing company is using Dynamics 365 Supply Chain Management and wants to take advantage of the asset management capabilities. The company has a fleet of delivery…

The correct answer is Counter; Time. Dynamics 365 Asset Management: Maintenance Plan Line Types Core Concept In Dynamics 365 Supply Chain Management, maintenance plan lines define when maintenance is triggered. The two plan types correspond to different measurement systems: | Plan Type | Triggered By | Example…

Implement asset management

Question

Drag and Drop Question A manufacturing company is using Dynamics 365 Supply Chain Management and wants to take advantage of the asset management capabilities. The company has a fleet of delivery trucks and wants to maintain the trucks to maximize the vehicle's performance and lifespan while minimizing the risk of breakdowns. To meet these requirements, the asset maintenance plan for the trucks should be configured with the following: - Require an oil change every 25,000 miles. - Require a comprehensive inspection every six months. You need to determine how to configure the asset maintenance plan lines for the delivery trucks. How should you configure the maintenance plan line? To answer, move the appropriate plan type to the correct requirement. You may use each plan type once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content. NOTE: Each correct selection is worth one point. Answer:

Exhibit

MB-330 question #414 exhibit

Answer Area

Drag items

CounterTime

Correct arrangement

  • Counter
  • Time

Explanation

Dynamics 365 Asset Management: Maintenance Plan Line Types

Core Concept

In Dynamics 365 Supply Chain Management, maintenance plan lines define when maintenance is triggered. The two plan types correspond to different measurement systems:

Plan TypeTriggered ByExample Unit
CounterA measurable quantity that accumulatesMiles, hours, cycles
TimeCalendar elapsed timeDays, weeks, months

Placement Breakdown

Requirement 1: Oil change every 25,000 miles → Counter

  • Mileage is a counter - it accumulates incrementally as the truck is used.
  • In D365, counters are registered against an asset (the truck) and the maintenance plan triggers when the counter reaches a defined threshold (25,000 miles).
  • The maintenance fires based on usage, not the passage of calendar time.

Requirement 2: Comprehensive inspection every six months → Time

  • "Every six months" is purely calendar-based - it doesn't matter how many miles were driven.
  • A Time-based plan line uses a recurrence interval (e.g., 6 months) tied to a calendar date.
  • The maintenance triggers when the specified time period elapses since the last work order.

Common Mistakes / Misconceptions

  • Using Time for mileage: A truck sitting idle for months would trigger an oil change even at 0 new miles. Counter correctly ties the trigger to actual vehicle use.
  • Using Counter for inspections: If a counter isn't registered (truck is idle), the inspection might never fire - dangerous for a safety-critical check that should happen regardless of usage.
  • Confusing "schedule" with "plan type": Both use a maintenance plan, but the line type dictates the trigger mechanism, not the frequency number.

Summary

Counter = trigger on accumulated usage (miles, hours) Time = trigger on elapsed calendar time (days, months, years)