MB-330 · Question #296
A company uses the built-in master planning engine but plans to use Planning Optimization instead. You enable auto-firming. You need to ensure that planned orders are firmed within the current…
The correct answer is D. Set the firming time fence to one month. You've hit your limit · resets 4am (America/New_York)
Implement master planning
Question
A company uses the built-in master planning engine but plans to use Planning Optimization instead. You enable auto-firming. You need to ensure that planned orders are firmed within the current month. What should you do?
Options
- ASet the firming time fence to one month plus issue margin.
- BSet the firming time fence to one month plus receipt margin
- CSet the firming time fence to one month plus lead lime rf the lead time is greater than one week.
- DSet the firming time fence to one month
- ESet the firming time fence to one week plus lead time if the lead time is less than one week.
How the community answered
(60 responses)- A5% (3)
- B2% (1)
- C8% (5)
- D83% (50)
- E2% (1)
Explanation
You've hit your limit · resets 4am (America/New_York)
Topics
#Planning Optimization#auto-firming#firming time fence#planned orders