A company performs internal inspections of a specific product before releasing the products. This task adds two days for product handling once the product is in the warehouse. This process leads to…

The correct answer is D. Maximum order quantity. https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/safety-margins

Implement master planning

Question

A company performs internal inspections of a specific product before releasing the products. This task adds two days for product handling once the product is in the warehouse. This process leads to delays in shipping. You need to resolve the issues. What should you change?

Options

  • AReorder margin
  • BMinimum order quantity
  • CReceipt margin
  • DMaximum order quantity
  • EIssue margin

How the community answered

(70 responses)
  • A
    4% (3)
  • B
    1% (1)
  • C
    16% (11)
  • D
    73% (51)
  • E
    6% (4)

Explanation

https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/safety-margins

Topics

#issue margin#receipt margin#warehouse handling#shipping lead time