A company uses Planning Optimization. A customer calls a service agent at the company and asks about product availability dates when placing an order. Capable to promise (CTP) is initiated from the…
The correct answer is A. An error occurs because CTP is not supported when Planning Optimization is enabled. https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/planning-optimization-trouble-shooting
Implement master planning
Question
A company uses Planning Optimization. A customer calls a service agent at the company and asks about product availability dates when placing an order. Capable to promise (CTP) is initiated from the customer's order. What is the expected output? Select only one answer.
Options
- AAn error occurs because CTP is not supported when Planning Optimization is enabled.
- BBuilt-in master planning runs the calculation if the master plan has a separate dynamic master
- CA warning shows in the plan history log.
- DCTP runs if add-ins are installed from Feature management.
- ECTP calculates if all Planning Optimization jobs are withheld from batch scheduling.
How the community answered
(69 responses)- A94% (65)
- B1% (1)
- D1% (1)
- E3% (2)
Explanation
https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/planning-optimization-trouble-shooting
Topics
#Planning Optimization#capable to promise#CTP#order availability