MB-330 · Question #240

You are making use of planning optimization in Dynamics 365 Supply Chain Management. When a planning optimization job, which is configured with the wrong runtime filters, is accidentally triggered…

The correct answer is A. You should access the plan history to cancel the job. https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/cancel-planning-job

Implement master planning

Question

You are making use of planning optimization in Dynamics 365 Supply Chain Management. When a planning optimization job, which is configured with the wrong runtime filters, is accidentally triggered from the user interface, you are tasked with fixing the problem. Which of the following actions should you take?

Options

  • AYou should access the plan history to cancel the job.
  • BYou should access the dialog box to cancel the job.
  • CYou should access the plan history to rectify runtime filters.
  • DYou should access the dialog box to rectify runtime filters.

How the community answered

(45 responses)
  • A
    73% (33)
  • B
    13% (6)
  • C
    9% (4)
  • D
    4% (2)

Explanation

https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/cancel-planning-job

Topics

#planning optimization#plan history#job cancellation#runtime filters