A company uses planning optimization in Dynamics 365 Supply Chain Management. Automatic firming is enabled. Some of the planned purchase orders are not being firmed as expected. The inventory…

The correct answer is A. Lead Time B. Automatic firming time fence (days). https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/ planning-optimization-auto-firming

Implement master planning

Question

A company uses planning optimization in Dynamics 365 Supply Chain Management. Automatic firming is enabled. Some of the planned purchase orders are not being firmed as expected. The inventory planners therefore need to manually process planned purchase orders. You need to include the planned purchase orders in automatic firming. What are two possible configurations you can use? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.

Options

  • ALead Time
  • BAutomatic firming time fence (days)
  • CRequirements Date
  • DFreeze time fence on master plan

How the community answered

(26 responses)
  • A
    69% (18)
  • C
    19% (5)
  • D
    12% (3)

Explanation

https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/ planning-optimization-auto-firming

Topics

#automatic firming#planning optimization#firming time fence#planned purchase orders