ITIL-F · Question #378
When is it confirmed if a project's objectives have been achieved?
The correct answer is A. During the Closing a Project process. See the full explanation below for the reasoning.
Question
When is it confirmed if a project's objectives have been achieved?
Options
- ADuring the Closing a Project process
- BDuring the final end stage assessment
- CDuring the Controlling a Stage process
- DDuring the Managing Product Delivery process
How the community answered
(37 responses)- A76% (28)
- B8% (3)
- C3% (1)
- D14% (5)