ITIL-F · Question #378

When is it confirmed if a project's objectives have been achieved?

The correct answer is A. During the Closing a Project process. See the full explanation below for the reasoning.

Question

When is it confirmed if a project's objectives have been achieved?

Options

  • ADuring the Closing a Project process
  • BDuring the final end stage assessment
  • CDuring the Controlling a Stage process
  • DDuring the Managing Product Delivery process

How the community answered

(37 responses)
  • A
    76% (28)
  • B
    8% (3)
  • C
    3% (1)
  • D
    14% (5)