Check, Act and Plan are three of the stages of the Deming Cycle. Which is the fourth?

The correct answer is A. Do. See the full explanation below for the reasoning.

Question

Check, Act and Plan are three of the stages of the Deming Cycle. Which is the fourth?

Options

  • ADo
  • BPerform
  • CImplement
  • DMeasure

How the community answered

(29 responses)
  • A
    76% (22)
  • B
    3% (1)
  • C
    7% (2)
  • D
    14% (4)