ISTQB-CTFL · Question #105
Which of the following statements about estimation of the test effort is WRONG?
The correct answer is C. Effort estimate depends on the budget of the project. Effort estimate does not depend on the budget of the project, but rather on the scope, complexity, and quality of the software product and the testing activities. Budget is a constraint that may affect the feasibility and accuracy of the effort estimate, but it is not a factor…
Question
Which of the following statements about estimation of the test effort is WRONG?
Options
- AOnce the test effort is estimated, resources can be identified and a schedule can be drawn up.
- BEffort estimate can be inaccurate because the quality of the product under tests is not known.
- CEffort estimate depends on the budget of the project.
- DExperience based estimation is one of the estimation techniques.
How the community answered
(25 responses)- A4% (1)
- C96% (24)
Explanation
Effort estimate does not depend on the budget of the project, but rather on the scope, complexity, and quality of the software product and the testing activities. Budget is a constraint that may affect the feasibility and accuracy of the effort estimate, but it is not a factor that determines the effort estimate. Effort estimate is the amount of work required to complete the testing activities, measured in terms of person-hours, person-days, or person-months.