What details should be recorded as a baseline prior to implementing a plan for service improvement?
The correct answer is C. Correct. The standard recommends the collection of service quality and levels as a baseline so. may be other details too. be other details too. that actual improvement can be measured. other details too.
Continual Improvement
Question
What details should be recorded as a baseline prior to implementing a plan for service improvement?
Options
- AIncorrect. This may be one of the measures if backlog of changes is to be reduced but there
- BIncorrect. This may be one of the measures if staff numbers are to be improved but there may
- CCorrect. The standard recommends the collection of service quality and levels as a baseline so
- DIncorrect. This may be one of the measures if time taken is to be improved but there may be
How the community answered
(51 responses)- A14% (7)
- B6% (3)
- C76% (39)
- D4% (2)
Explanation
may be other details too. be other details too. that actual improvement can be measured. other details too.
Topics
#service improvement#baseline measurement#service quality#service levels