BCS-ISEB
ISEB-SWT2 · Question #79
Which of the following is a MAJOR activity of test planning?
The correct answer is C. Determining the exit criteria. See the full explanation below for the reasoning.
Question
Which of the following is a MAJOR activity of test planning?
Options
- AInitiation of corrective actions
- BMeasuring and analysing results
- CDetermining the exit criteria
- DMonitoring and documenting progress
How the community answered
(29 responses)- A21% (6)
- B3% (1)
- C69% (20)
- D7% (2)
Community Discussion
No community discussion yet for this question.