BCS-ISEB
ISEB-SWT2 · Question #7
How is the scope of maintenance testing assessed?
The correct answer is A. Scope is related to the risk, size of the changes and size of the system under test. See the full explanation below for the reasoning.
Question
How is the scope of maintenance testing assessed?
Options
- AScope is related to the risk, size of the changes and size of the system under test
- BScope is defined by the size and type of system being changed
- CScope is defined by the size and type of system being changed
- DScope is related to the number of system users affected by the change.
How the community answered
(50 responses)- A80% (40)
- B6% (3)
- C2% (1)
- D12% (6)
Community Discussion