When in the lifecycle should testing activities start?
The correct answer is A. As early as possible. See the full explanation below for the reasoning.
Question
When in the lifecycle should testing activities start?
Options
- AAs early as possible
- BAfter the test environment is ready
- CAfter the requirements have been reviewed
- DOnce the code is available to test
How the community answered
(70 responses)- A76% (53)
- B7% (5)
- C13% (9)
- D4% (3)