ISEB-PM1 · Question #61
Executing the risk response plan in order to react to risk events throughout the project is called:
The correct answer is B. Monitoring and control. You've hit your session limit · resets 10:20pm (America/New_York)
Risk Management
Question
Executing the risk response plan in order to react to risk events throughout the project is called:
Options
- AContingency planning.
- BMonitoring and control.
- CMitigation.
- DLife cycle costing.
How the community answered
(25 responses)- A12% (3)
- B80% (20)
- C4% (1)
- D4% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#risk monitoring#risk response execution#monitor and control risks#risk management process