What are the performance measurements for the Schedule Control process?
The correct answer is A. SV (EV - PV) and SPI (EV ?PV). You've hit your weekly limit · resets 5am (America/New_York)
Project Control
Question
What are the performance measurements for the Schedule Control process?
Options
- ASV (EV - PV) and SPI (EV ?PV)
- BSV (PV - EV) and SPI (PV ?EV)
- CSV (EV - BAC) and SPI (EV ?BAC)
- DSV (EV - AC) and SPI (EV ?AC)
How the community answered
(43 responses)- A84% (36)
- B9% (4)
- C2% (1)
- D5% (2)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#schedule variance#schedule performance index#earned value management#schedule control