ISEB-PM1 · Question #581

What are the performance measurements for the Schedule Control process?

The correct answer is A. SV (EV - PV) and SPI (EV ?PV). You've hit your weekly limit · resets 5am (America/New_York)

Project Control

Question

What are the performance measurements for the Schedule Control process?

Options

  • ASV (EV - PV) and SPI (EV ?PV)
  • BSV (PV - EV) and SPI (PV ?EV)
  • CSV (EV - BAC) and SPI (EV ?BAC)
  • DSV (EV - AC) and SPI (EV ?AC)

How the community answered

(43 responses)
  • A
    84% (36)
  • B
    9% (4)
  • C
    2% (1)
  • D
    5% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#schedule variance#schedule performance index#earned value management#schedule control