nerdexam
BCS-ISEB

ISEB-PM1 · Question #503

Which of the following equations is used to calculate cost variance?

The correct answer is A. EV-AC. Cost Variance (CV) = EV − AC (option A), where Earned Value minus Actual Cost tells you whether you're under or over budget - a positive result means under budget, negative means over. Option B (AC − EV) simply reverses the formula, flipping the sign and making over-budget look…

Project Control

Question

Which of the following equations is used to calculate cost variance?

Options

  • AEV-AC
  • BAC-EV
  • CAC+EV
  • DAC/EV

How the community answered

(56 responses)
  • A
    73% (41)
  • B
    9% (5)
  • C
    14% (8)
  • D
    4% (2)

Explanation

Cost Variance (CV) = EV − AC (option A), where Earned Value minus Actual Cost tells you whether you're under or over budget - a positive result means under budget, negative means over. Option B (AC − EV) simply reverses the formula, flipping the sign and making over-budget look positive, which contradicts the standard interpretation. Options C and D (AC + EV and AC / EV) are not standard earned value formulas at all - addition and division of these two metrics produce meaningless results for variance purposes. A handy memory tip: "CV = EV − AC" follows alphabetical order (E before A), so remember E comes before A in Cost Variance, just as it does in the alphabet.

Topics

#cost variance#earned value management#EV#AC

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice