Which of the following is an input to identify risk?
The correct answer is A. Organizational process assets. Organizational process assets (OPAs) are a recognized input to the Identify Risks process because they contain historical information, lessons learned from past projects, risk templates, and organizational knowledge that directly inform what risks to look for - you can't…
Question
Which of the following is an input to identify risk?
Options
- AOrganizational process assets
- BScope management plan
- CCommunication management plan
- DExpert judgment
How the community answered
(33 responses)- A76% (25)
- B3% (1)
- C6% (2)
- D15% (5)
Explanation
Organizational process assets (OPAs) are a recognized input to the Identify Risks process because they contain historical information, lessons learned from past projects, risk templates, and organizational knowledge that directly inform what risks to look for - you can't identify risks in a vacuum without context from prior experience.
Option B (Scope management plan) and Option C (Communication management plan) are both components of the project management plan, but neither is specifically listed as a standalone input to Identify Risks; they govern how scope and communications are managed, not risk identification itself.
Option D (Expert judgment) is the most tempting distractor - it's commonly used in risk identification, but it's a tool and technique, not an input. The PMBOK distinguishes clearly between ITTOs (Inputs, Tools/Techniques, Outputs), and Expert judgment consistently appears in the tools column.
Memory tip: For any PMBOK process, remember that OPAs and Enterprise Environmental Factors (EEFs) are almost always inputs - they feed into the process. Expert judgment is almost always a tool, never an input. If you see "Expert judgment" listed as an input choice, it's virtually always wrong.