ISEB-PM1 · Question #434
If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?
The correct answer is D. $66. Option D ($66) is correct because the Schedule Variance formula is SV = EV − PV, so rearranging gives EV = SV + PV = $55 + $11 = $66. Why the distractors fail: A ($0.2) - Results from dividing PV ÷ SV ($11 ÷ $55), which has no basis in Earned Value Management formulas. B ($5)…
Question
If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?
Options
- A$0.2
- B$5
- C$44
- D$66
How the community answered
(49 responses)- A6% (3)
- B4% (2)
- C12% (6)
- D78% (38)
Explanation
Option D ($66) is correct because the Schedule Variance formula is SV = EV − PV, so rearranging gives EV = SV + PV = $55 + $11 = $66.
Why the distractors fail:
- A ($0.2) - Results from dividing PV ÷ SV ($11 ÷ $55), which has no basis in Earned Value Management formulas.
- B ($5) - Results from dividing SV ÷ PV ($55 ÷ $11 = 5), which actually calculates the Schedule Performance Index (SPI), not EV.
- C ($44) - Results from subtracting PV from SV ($55 − $11), which reverses the correct rearrangement; you must add PV, not subtract it.
Memory tip: Anchor the formula as "SV = EV − PV" and remember it alphabetically - E comes before P, so EV minus PV. To isolate EV, just move PV to the other side: EV = SV + PV.
Topics
Community Discussion
No community discussion yet for this question.