BCS-ISEB
ISEB-PM1 · Question #402
Which one of the following is true regarding the change control board?
The correct answer is B. Approves or rejects change requests. See the full explanation below for the reasoning.
Project Control
Question
Which one of the following is true regarding the change control board?
Options
- ADescribes how changes are managed.
- BApproves or rejects change requests.
- CNeeds updated project management plans to approve or reject a change.
- DDescribes how changes are documented.
How the community answered
(70 responses)- A13% (9)
- B80% (56)
- C4% (3)
- D3% (2)
Topics
#change control board#change requests#change approval#governance
Community Discussion
No community discussion yet for this question.