ISEB-PM1 · Question #255
Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?
The correct answer is B. -$2,000. Cost Variance (CV) = EV − AC, so $20,000 − $22,000 = −$2,000, making B correct - the project is over budget by $2,000 because you spent more than the work is worth. Why the distractors are wrong: A (−$8,000) is the Schedule Variance (SV = EV − PV = $20,000 − $28,000), not CV…
Question
Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?
Options
- A-$8,000
- B-$2,000
- C$2,000
- D$8,000
How the community answered
(17 responses)- A12% (2)
- B82% (14)
- C6% (1)
Explanation
Cost Variance (CV) = EV − AC, so $20,000 − $22,000 = −$2,000, making B correct - the project is over budget by $2,000 because you spent more than the work is worth.
Why the distractors are wrong:
- A (−$8,000) is the Schedule Variance (SV = EV − PV = $20,000 − $28,000), not CV - a common mix-up when all three metrics are given.
- C ($2,000) is the result of flipping the subtraction (AC − EV reversed), ignoring the correct formula order.
- D ($8,000) reverses the SV formula (PV − EV), which is neither CV nor SV correctly calculated.
Memory tip: Think "CV = EV minus AC" - alphabetically, E comes before A, so subtract in that order. A negative CV always means over budget (you paid more than the value earned).
Topics
Community Discussion
No community discussion yet for this question.