ISEB-PM1 · Question #252
The PV is $1000, EV is $2000 and AC is $1500. What is CPI?
The correct answer is A. 1.33. CPI (Cost Performance Index) = EV ÷ AC = $2000 ÷ $1500 = 1.33, making option A correct - a CPI above 1.0 means you're getting more value than you're spending, so the project is under budget. Option B (2.00) confuses CPI with SPI (Schedule Performance Index): EV ÷ PV = $2000 ÷…
Question
The PV is $1000, EV is $2000 and AC is $1500. What is CPI?
Options
- A1.33
- B2.00
- C0.75
- D0.5
How the community answered
(51 responses)- A73% (37)
- B14% (7)
- C10% (5)
- D4% (2)
Explanation
CPI (Cost Performance Index) = EV ÷ AC = $2000 ÷ $1500 = 1.33, making option A correct - a CPI above 1.0 means you're getting more value than you're spending, so the project is under budget.
Option B (2.00) confuses CPI with SPI (Schedule Performance Index): EV ÷ PV = $2000 ÷ $1000 = 2.00 measures schedule efficiency, not cost. Option C (0.75) inverts the formula, calculating AC ÷ EV instead of EV ÷ AC. Option D (0.5) inverts the SPI formula (PV ÷ EV), which has nothing to do with cost performance.
Memory tip: "Earned Value always goes on top" - both CPI and SPI use EV as the numerator; what changes is the denominator: CPI uses AC (cost), SPI uses PV (schedule/plan).
Topics
Community Discussion
No community discussion yet for this question.