nerdexam
BCS-ISEB

ISEB-PM1 · Question #218

Who MUST know when a risk event occurs so that a response can be implemented?

The correct answer is C. Project management team. The project management team must know when a risk event occurs because they are responsible for executing the risk response plan - they own the day-to-day monitoring of risks and are positioned to activate contingency plans immediately when a trigger is detected. Why the…

Risk Management

Question

Who MUST know when a risk event occurs so that a response can be implemented?

Options

  • ACustomers
  • BProject sponsors
  • CProject management team
  • DInsurance claims department

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    17% (5)
  • C
    69% (20)
  • D
    3% (1)

Explanation

The project management team must know when a risk event occurs because they are responsible for executing the risk response plan - they own the day-to-day monitoring of risks and are positioned to activate contingency plans immediately when a trigger is detected.

Why the distractors are wrong:

  • A (Customers): Customers are stakeholders who may need to be informed of impacts, but they are not responsible for implementing risk responses.
  • B (Project sponsors): Sponsors provide oversight and funding authority but are typically escalated to only for major risks, not every risk event - that's the management team's job.
  • D (Insurance claims department): Only relevant if a risk involves an insured loss; this is far too narrow and reactive to apply broadly to project risk management.

Memory tip: Think of risk response as a fire drill - the fire department (project management team) must know first so they can act. You might notify the building owner (sponsor) or tenants (customers) afterward, but the response team goes first.

Topics

#risk response#risk event#project management team#risk owner

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice