ISEB-PM1 · Question #218
Who MUST know when a risk event occurs so that a response can be implemented?
The correct answer is C. Project management team. The project management team must know when a risk event occurs because they are responsible for executing the risk response plan - they own the day-to-day monitoring of risks and are positioned to activate contingency plans immediately when a trigger is detected. Why the…
Question
Who MUST know when a risk event occurs so that a response can be implemented?
Options
- ACustomers
- BProject sponsors
- CProject management team
- DInsurance claims department
How the community answered
(29 responses)- A10% (3)
- B17% (5)
- C69% (20)
- D3% (1)
Explanation
The project management team must know when a risk event occurs because they are responsible for executing the risk response plan - they own the day-to-day monitoring of risks and are positioned to activate contingency plans immediately when a trigger is detected.
Why the distractors are wrong:
- A (Customers): Customers are stakeholders who may need to be informed of impacts, but they are not responsible for implementing risk responses.
- B (Project sponsors): Sponsors provide oversight and funding authority but are typically escalated to only for major risks, not every risk event - that's the management team's job.
- D (Insurance claims department): Only relevant if a risk involves an insured loss; this is far too narrow and reactive to apply broadly to project risk management.
Memory tip: Think of risk response as a fire drill - the fire department (project management team) must know first so they can act. You might notify the building owner (sponsor) or tenants (customers) afterward, but the response team goes first.