A non-critical path activity is completed in half the time. Then, ISEB ISEB-PM1 Exam
The correct answer is B. The slack in the path containing this activity will increase. You've hit your session limit · resets 10:20pm (America/New_York)
Project Control
Question
A non-critical path activity is completed in half the time. Then, ISEB ISEB-PM1 Exam
Options
- AAll of the other alternatives apply.
- BThe slack in the path containing this activity will increase.
- CThe total cost for this activity has decreased.
- DThe critical path is also reduced.
- EManpower from this activity can be assigned to other activities.
How the community answered
(61 responses)- A2% (1)
- B79% (48)
- C11% (7)
- D7% (4)
- E2% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#critical path#float#slack#schedule analysis