A non-critical path activity is completed in half the time. Then, ISEB ISEB-PM1 Exam

The correct answer is B. The slack in the path containing this activity will increase. You've hit your session limit · resets 10:20pm (America/New_York)

Project Control

Question

A non-critical path activity is completed in half the time. Then, ISEB ISEB-PM1 Exam

Options

  • AAll of the other alternatives apply.
  • BThe slack in the path containing this activity will increase.
  • CThe total cost for this activity has decreased.
  • DThe critical path is also reduced.
  • EManpower from this activity can be assigned to other activities.

How the community answered

(61 responses)
  • A
    2% (1)
  • B
    79% (48)
  • C
    11% (7)
  • D
    7% (4)
  • E
    2% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#critical path#float#slack#schedule analysis

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice