ISEB-PM1 · Question #161

You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product…

The correct answer is A. Performance measurement baselines might be affected by scope changes. You've hit your session limit · resets 10:20pm (America/New_York)

Project Control

Question

You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the project scope. Which of the following statements is true?

Options

  • APerformance measurement baselines might be affected by scope changes.
  • BProject scope change uses workarounds to correct unexpected problems with scope change.
  • CProject scope change uses inspection to determine whether change has occurred.
  • DProject scope changes do not require CCB approval.

How the community answered

(23 responses)
  • A
    70% (16)
  • B
    9% (2)
  • C
    17% (4)
  • D
    4% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#scope change#performance baseline#change control board#change management