Which of these would fall outside the scope of a typical service change management process

The correct answer is C. A change to a business process that depends on IT Services. See the full explanation below for the reasoning.

Question

Which of these would fall outside the scope of a typical service change management process

Options

  • AAn urgent need to replace a CPU to restore a service during an incident
  • BA change to a contract with a supplier
  • CA change to a business process that depends on IT Services
  • DA firmware upgrade to a server that is only used for IT Service Continuity purposes

How the community answered

(47 responses)
  • A
    9% (4)
  • B
    2% (1)
  • C
    85% (40)
  • D
    4% (2)