IIA-CIA-PART1 · Question #76
Which of the following would best assist the internal audit activity in assessing whether an organization's responses to risk are aligned with its risk appetite?
The correct answer is A. Analyzing the results of successful testing of controls and monitoring procedures implemented by. Option A is correct because testing controls and monitoring procedures directly verifies whether the risk responses management put in place are actually functioning to keep risks within the organization's defined risk appetite - if controls are working as designed, risks are…
Question
Which of the following would best assist the internal audit activity in assessing whether an organization's responses to risk are aligned with its risk appetite?
Options
- AAnalyzing the results of successful testing of controls and monitoring procedures implemented by
- BDetermining that there are no gaps between the internal auditors' risk assessment and the risk
- CObtaining evidence that employees throughout the organization are aware of the organization s
- DVerifying that previously identified organizational risks were documented in board meeting
How the community answered
(46 responses)- A78% (36)
- B4% (2)
- C7% (3)
- D11% (5)
Explanation
Option A is correct because testing controls and monitoring procedures directly verifies whether the risk responses management put in place are actually functioning to keep risks within the organization's defined risk appetite - if controls are working as designed, risks are being managed to acceptable levels.
Why the distractors fall short:
- B compares the auditors' own risk assessment to another risk assessment - this reveals alignment between assessments, not between responses and risk appetite. Assessments agreeing doesn't confirm risks are being managed appropriately.
- C checks employee awareness of policies, but awareness alone doesn't confirm that actual risk responses are calibrated to appetite. You can know the speed limit and still drive too fast.
- D verifying board documentation of past risks shows record-keeping, not whether management's responses are keeping risks within acceptable bounds going forward.
Memory tip: Think of it as "evidence of effect, not intent." Options B, C, and D all deal with documentation, awareness, or assessments - they show that people know about risks. Option A is the only one that tests whether risk responses are actually doing their job, which is what "aligned with risk appetite" means in practice.