nerdexam
IIA

IIA-CIA-PART1 · Question #81

What would be the proper sequence of steps for an internal auditor to take in order to draw a conclusion on internal control effectiveness and adequacy after ascertaining the key controls?

The correct answer is A. Evaluate the adequacy of the controls and then test the controls for effectiveness. Option A is correct because the logical sequence after identifying key controls is to first evaluate adequacy (asking "are these controls well-designed to address the risk?") and then test for effectiveness (asking "are they actually working in practice?") - you must confirm a…

Question

What would be the proper sequence of steps for an internal auditor to take in order to draw a conclusion on internal control effectiveness and adequacy after ascertaining the key controls?

Options

  • AEvaluate the adequacy of the controls and then test the controls for effectiveness.
  • BTest the controls for effectiveness and then evaluate the adequacy of the controls.
  • CIdentify risks and then evaluate the controls for effectiveness.
  • DEvaluate the controls for effectiveness and then assess the risks in the area.

How the community answered

(28 responses)
  • A
    71% (20)
  • B
    4% (1)
  • C
    18% (5)
  • D
    7% (2)

Explanation

Option A is correct because the logical sequence after identifying key controls is to first evaluate adequacy (asking "are these controls well-designed to address the risk?") and then test for effectiveness (asking "are they actually working in practice?") - you must confirm a control is properly designed before investing time testing whether it operates as intended.

Why the distractors fail:

  • B reverses the order: testing a control for effectiveness before knowing if it's adequately designed wastes effort - a poorly designed control can "work as designed" and still leave risks unmitigated.
  • C misplaces the step - risk identification occurs before ascertaining key controls, not after; the question specifies you've already completed that earlier phase.
  • D also reverses logic: assessing risks comes early in the audit process, not as a conclusion step after evaluating effectiveness.

Memory tip: Think of it as a builder's checklist - first confirm the blueprint is sound (adequacy), then inspect whether construction followed it (effectiveness). You wouldn't inspect construction quality on a flawed blueprint.

Community Discussion

No community discussion yet for this question.

Full IIA-CIA-PART1 Practice