If the skills and competencies are not present within the internal audit activity to complete an ad-hoc assurance engagement, which of the following is an acceptable resolution?
The correct answer is C. Consider using employees from other departments in the organization on the audit team. Option C is correct because IIA Standard 1210 (Proficiency) requires the internal audit activity to possess or obtain the knowledge, skills, and competencies needed to perform its responsibilities - and one acceptable way to obtain missing competencies is by leveraging…
Question
If the skills and competencies are not present within the internal audit activity to complete an ad-hoc assurance engagement, which of the following is an acceptable resolution?
Options
- APolitely decline the engagement due to a lack of qualified staff available at the time.
- BComplete the engagement as requested, with the best of the current staffs abilities.
- CConsider using employees from other departments in the organization on the audit team.
- DChange the scope of the testing to ensure that only available staff proficiencies are used
How the community answered
(49 responses)- A14% (7)
- B6% (3)
- C78% (38)
- D2% (1)
Explanation
Option C is correct because IIA Standard 1210 (Proficiency) requires the internal audit activity to possess or obtain the knowledge, skills, and competencies needed to perform its responsibilities - and one acceptable way to obtain missing competencies is by leveraging qualified staff from other parts of the organization as guest auditors or co-sourcing partners.
- A is wrong because simply declining is not the appropriate resolution; the IIA standards expect the CAE to find a way to fulfill the engagement, not abandon it.
- B is wrong because proceeding without the required competencies violates the proficiency standard and risks issuing an unreliable opinion, which could harm the organization.
- D is wrong because arbitrarily narrowing scope to match staff limitations - rather than matching staff to scope - compromises the integrity and purpose of the engagement.
Memory tip: Think of it as "borrow before you bail" - when internal talent is lacking, borrow qualified people from elsewhere in the organization (or use external resources) before declining or compromising the engagement.