HPE7-A06 · Question #82
Refer to the exhibit. Based on the screenshot, what is required to correct the state displayed in the exhibit?
The correct answer is A. Use the same OS-CX image on the secondary that is active on primary. The exhibit shows that the VSX config-sync is non-operational with the error state SW version mismatch. This occurs when the primary and secondary switches are running different ArubaOS- CX software versions. To correct this, both peers must run the same OS-CX image. The…
Question
Refer to the exhibit. Based on the screenshot, what is required to correct the state displayed in the exhibit?
Exhibit
Options
- AUse the same OS-CX image on the secondary that is active on primary.
- BUse copy running-config vsx-peer on the secondary switch.
- CUse the Enhanced Software Update process to correct the state.
- DUse the force vsx-sync to start sync process.
How the community answered
(60 responses)- A72% (43)
- B7% (4)
- C17% (10)
- D5% (3)
Explanation
The exhibit shows that the VSX config-sync is non-operational with the error state SW version mismatch. This occurs when the primary and secondary switches are running different ArubaOS- CX software versions. To correct this, both peers must run the same OS-CX image. The recommended remediation explicitly suggests running show images to confirm the software image and ensure the same version is loaded on both peers.