HPE7-A06 · Question #16
With the configuration of two CX 8325 switches in the VSX cluster, how would you prepare a link- aggregation for a 7000 gateway for a zero-touch provision to support protocol-based port redundancy? A.
The correct answer is A. int lag 1 multi-chassis lacp mode active lacp fallback. For a 7000 gateway ZTP with protocol-based port redundancy on a VSX pair, the LAG must be multi-chassis with LACP active; lacp fallback allows a single member to come up until the peer is discovered, ensuring connectivity during provisioning.
Question
With the configuration of two CX 8325 switches in the VSX cluster, how would you prepare a link- aggregation for a 7000 gateway for a zero-touch provision to support protocol-based port redundancy? A. B. C. D.
Options
- Aint lag 1 multi-chassis lacp mode active lacp fallback
- Bint lag 1 lacp mode active lacp fallback
- Cint lag 1 multi-chassis lacp mode on lacp fallback
- Dint lag 1 lacp mode on lacp fallback
How the community answered
(45 responses)- A58% (26)
- B11% (5)
- C24% (11)
- D7% (3)
Explanation
For a 7000 gateway ZTP with protocol-based port redundancy on a VSX pair, the LAG must be multi-chassis with LACP active; lacp fallback allows a single member to come up until the peer is discovered, ensuring connectivity during provisioning.
Topics
Community Discussion