HPE7-A04 · Question #61
Which of the following are deemed as Post-installation handover tasks
The correct answer is B. Enable monitoring of new systems. Enabling monitoring of new systems (B) is a post-installation handover task because it occurs after deployment is complete - you hand over a functioning, observable system to the operations or client team, which requires activating monitoring tools so the new system can be…
Question
Which of the following are deemed as Post-installation handover tasks
Options
- AProject budget details
- BEnable monitoring of new systems
- CRFP
How the community answered
(32 responses)- A9% (3)
- B88% (28)
- C3% (1)
Explanation
Enabling monitoring of new systems (B) is a post-installation handover task because it occurs after deployment is complete - you hand over a functioning, observable system to the operations or client team, which requires activating monitoring tools so the new system can be tracked in production.
Why the distractors are wrong:
- A (Project budget details) belongs to the planning or procurement phase, not post-installation. Budget is finalized before work begins, not during handover.
- C (RFP - Request for Proposal) is a pre-project procurement document used to solicit vendor bids. It has no role after installation is done.
Memory tip: Think of handover as "handing the keys to the new owner." The new owner needs the system running and watched (monitoring), not a sales document (RFP) or a spending plan (budget) - those are pre-move paperwork.