HPE7-A04 · Question #19
Name some Post-installation handover tasks
The correct answer is A. Ensure new spares have replaced old spares D. Schedule training. Post-installation handover tasks are actions taken to formally complete a project and transition responsibility to the client or end-users. Ensuring new spares replace old ones (A) is correct because confirming the availability of replacement parts is essential to ongoing…
Question
Name some Post-installation handover tasks
Options
- AEnsure new spares have replaced old spares
- BList of Engineers involved in the project
- CNumber of employees that will benefit from the solution
- DSchedule training
How the community answered
(24 responses)- A92% (22)
- B4% (1)
- C4% (1)
Explanation
Post-installation handover tasks are actions taken to formally complete a project and transition responsibility to the client or end-users. Ensuring new spares replace old ones (A) is correct because confirming the availability of replacement parts is essential to ongoing system maintenance after handover. Scheduling training (D) is correct because users and administrators must be equipped to operate the new system before the project is considered complete.
B (List of Engineers) is incorrect because recording who worked on the project is an internal project management or HR concern, not a handover deliverable that ensures the client can sustain the solution. C (Number of employees that will benefit) is incorrect because that figure belongs in the pre-project business case or benefits realization report, not in the handover checklist.
Memory tip: Think of handover tasks as anything the client needs going forward - spare parts to fix it and training to use it. If it only documents the past (who built it, why it was justified), it's not a handover task.