Question

The two-site three-center disaster recovery solution adopts the "active-active + synchronous + asynchronous parallel" networking architecture. Which of the following is wrong about its disaster switching processing?

Options

  • AAfter the off-site disaster recovery center takes over the business from the LUN, the array of the
  • BArray A in production center fails, but array B in production center continues to provide services.
  • CWhen both the arrays in production center A and production center B fail, the off-site disaster
  • DAfter the array B in the production center fails, the array A in the production center continues to