The correct answer is C. When both the arrays in production center A and production center B fail, the off-site disaster. See the full explanation below for the reasoning.
Question
The two-site three-center disaster recovery solution adopts the "active-active + synchronous + asynchronous parallel" networking architecture. Which of the following is wrong about its disaster switching processing?
Options
- AAfter the off-site disaster recovery center takes over the business from the LUN, the array of the
- BArray A in production center fails, but array B in production center continues to provide services.
- CWhen both the arrays in production center A and production center B fail, the off-site disaster
- DAfter the array B in the production center fails, the array A in the production center continues to