H13-629_V3.0 · Question #961
According to the calculation in the backup plan, the storage capacity required by site A is 3000GB, and the storage capacity required by site B is 1500GB. Now it is required to store the backup data…
The correct answer is D. 3500GB. See the full explanation below for the reasoning.
Data Protection and Business Continuity Solution Design
Question
According to the calculation in the backup plan, the storage capacity required by site A is 3000GB, and the storage capacity required by site B is 1500GB. Now it is required to store the backup data of site B remotely to site A, and the deduplication ratio is 3. Please plan the minimum backend storage capacity required by site A without considering the redundancy ratio?
Options
- A4500GB
- B1500GB
- C2500GB
- D3500GB
How the community answered
(25 responses)- A8% (2)
- B4% (1)
- C12% (3)
- D76% (19)
Topics
#backup capacity planning#deduplication ratio#remote backup#storage sizing