The following is a "five-step method" for disaster recovery plan design. Which of the following is the correct order of design steps?

The correct answer is D. Disaster recovery solution selection -> Compatibility confirmation -> Storage capacity consideration. See the full explanation below for the reasoning.

Data Protection and Business Continuity Solution Design

Question

The following is a "five-step method" for disaster recovery plan design. Which of the following is the correct order of design steps?

Options

  • AStorage capacity consideration and disaster recovery bandwidth calculation -> Compatibility
  • BCompatibility confirmation -> Storage capacity consideration and disaster recovery bandwidth
  • CStorage capacity consideration and disaster recovery bandwidth calculation -> Network design -
  • DDisaster recovery solution selection -> Compatibility confirmation -> Storage capacity consideration

How the community answered

(52 responses)
  • A
    6% (3)
  • B
    12% (6)
  • C
    2% (1)
  • D
    81% (42)

Topics

#disaster recovery planning#five-step method#DR plan design#design methodology