GSLC · Question #93
GSLC Question #93: Real Exam Question with Answer & Explanation
The correct answer is B. There will be a need for an additional project scope statement because of the change request.. This project management question tests understanding of integrated change control and what components are impacted when scope is expanded. Adding laptops affects time, procurement, and risk - but not the need for a separate scope statement.
Question
Options
- AThere will be a need for additional time to install the laptops.
- BThere will be a need for an additional project scope statement because of the change request.
- CThere will be a need for additional procurement management processes.
- DThere will be a need for additional risk analysis for the laptops.
Explanation
This project management question tests understanding of integrated change control and what components are impacted when scope is expanded. Adding laptops affects time, procurement, and risk - but not the need for a separate scope statement.
Common mistakes.
- A. Adding 250 laptops introduces additional configuration, imaging, and deployment work, directly increasing the time component of the project.
- C. Laptops are new hardware items not in the original procurement plan, so additional procurement management processes would be required to acquire them.
- D. New device types (laptops) introduce new risk considerations such as mobility-related theft, loss, or security vulnerabilities that must be analyzed.
Concept tested. Integrated change control impact on project components
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Community Discussion
No community discussion yet for this question.