You work as a project manager for an IT project. You are analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. In which of the…
The correct answer is B. Project Time Management. Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule describes the Develop Schedule process, which belongs to Project Time Management.
Question
You work as a project manager for an IT project. You are analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. In which of the following Knowledge Areas are you working on?
Options
- AProject Integration Management
- BProject Time Management
- CProject Scope Management
- DProject Risk Management
How the community answered
(34 responses)- A3% (1)
- B88% (30)
- C6% (2)
- D3% (1)
Why each option
Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule describes the Develop Schedule process, which belongs to Project Time Management.
Project Integration Management focuses on coordinating and unifying all project management processes and activities across the project, not on the detailed development of activity schedules.
Project Time Management encompasses all processes required to manage timely project completion, including Develop Schedule - a process that uses activity sequences, durations, resource requirements, and schedule constraints as inputs to produce the finalized project schedule baseline.
Project Scope Management is concerned with defining, validating, and controlling what is and is not included in the project, which is a separate concern from scheduling.
Project Risk Management covers identifying, analyzing, and planning responses to project risks and is a separate knowledge area from schedule development.
Concept tested: Project Time Management Develop Schedule process inputs