nerdexam
GIAC

GSLC · Question #566

The Project Scope Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is A. Create Work Breakdown Structure (WBS) B. Control Scope D. Verify Scope. Project Scope Management includes Create WBS, Control Scope, and Validate Scope (historically called Verify Scope); Select Sellers belongs to Project Procurement Management.

Security Program Management & Governance

Question

The Project Scope Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.

Options

  • ACreate Work Breakdown Structure (WBS)
  • BControl Scope
  • CSelect Sellers
  • DVerify Scope

How the community answered

(39 responses)
  • A
    92% (36)
  • C
    8% (3)

Why each option

Project Scope Management includes Create WBS, Control Scope, and Validate Scope (historically called Verify Scope); Select Sellers belongs to Project Procurement Management.

ACreate Work Breakdown Structure (WBS)Correct

Create WBS is a planning process in Project Scope Management that decomposes the total project scope and deliverables into smaller, manageable work packages.

BControl ScopeCorrect

Control Scope is a monitoring and controlling process in Project Scope Management that tracks the project scope status and manages changes to the scope baseline.

CSelect Sellers

Select Sellers is a process in the Project Procurement Management knowledge area, not Scope Management, because it involves evaluating bids and choosing suppliers or vendors.

DVerify ScopeCorrect

Verify Scope (renamed Validate Scope in later PMBOK editions) is a Project Scope Management process focused on formally obtaining stakeholder acceptance of completed project deliverables.

Concept tested: PMBOK Project Scope Management knowledge area processes

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#project scope management#WBS#scope verification#project management

Community Discussion

No community discussion yet for this question.

Full GSLC Practice