The correct answer is A. Create Work Breakdown Structure (WBS) B. Control Scope D. Verify Scope. Project Scope Management includes Create WBS, Control Scope, and Validate Scope (historically called Verify Scope); Select Sellers belongs to Project Procurement Management.
Question
The Project Scope Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.
Options
- ACreate Work Breakdown Structure (WBS)
- BControl Scope
- CSelect Sellers
- DVerify Scope
Explanation
Project Scope Management includes Create WBS, Control Scope, and Validate Scope (historically called Verify Scope); Select Sellers belongs to Project Procurement Management.
Common mistakes.
- C. Select Sellers is a process in the Project Procurement Management knowledge area, not Scope Management, because it involves evaluating bids and choosing suppliers or vendors.
Concept tested. PMBOK Project Scope Management knowledge area processes
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok