GSLC · Question #514
Which of the following are outputs of the Direct and Manage Project Execution process? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is A. Change requests B. Deliverables D. Work performance information. The PMBOK Direct and Manage Project Execution process produces deliverables, work performance information, and change requests. Project staff assignments belong to the Acquire Project Team process, not this one.
Question
Which of the following are outputs of the Direct and Manage Project Execution process? Each correct answer represents a complete solution. Choose all that apply.
Options
- AChange requests
- BDeliverables
- CProject staff assignments
- DWork performance information
How the community answered
(37 responses)- A86% (32)
- C14% (5)
Why each option
The PMBOK Direct and Manage Project Execution process produces deliverables, work performance information, and change requests. Project staff assignments belong to the Acquire Project Team process, not this one.
Change requests are generated during execution when deviations, issues, or new requirements arise that necessitate modifications to the project management plan or baselines.
Deliverables are the primary output of Direct and Manage Project Execution, representing the completed products, services, or results produced to satisfy project objectives.
Project staff assignments are an output of the Acquire Project Team process within Human Resource Management, not of the Direct and Manage Project Execution process.
Work performance information - such as deliverable completion status, schedule progress, and actual costs incurred - is collected continuously throughout execution and feeds into monitoring and controlling processes.
Concept tested: PMBOK Direct and Manage Project Execution process outputs
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok