nerdexam
GIAC

GSLC · Question #514

Which of the following are outputs of the Direct and Manage Project Execution process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is A. Change requests B. Deliverables D. Work performance information. The PMBOK Direct and Manage Project Execution process produces deliverables, work performance information, and change requests. Project staff assignments belong to the Acquire Project Team process, not this one.

Security Program Management & Governance

Question

Which of the following are outputs of the Direct and Manage Project Execution process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AChange requests
  • BDeliverables
  • CProject staff assignments
  • DWork performance information

How the community answered

(37 responses)
  • A
    86% (32)
  • C
    14% (5)

Why each option

The PMBOK Direct and Manage Project Execution process produces deliverables, work performance information, and change requests. Project staff assignments belong to the Acquire Project Team process, not this one.

AChange requestsCorrect

Change requests are generated during execution when deviations, issues, or new requirements arise that necessitate modifications to the project management plan or baselines.

BDeliverablesCorrect

Deliverables are the primary output of Direct and Manage Project Execution, representing the completed products, services, or results produced to satisfy project objectives.

CProject staff assignments

Project staff assignments are an output of the Acquire Project Team process within Human Resource Management, not of the Direct and Manage Project Execution process.

DWork performance informationCorrect

Work performance information - such as deliverable completion status, schedule progress, and actual costs incurred - is collected continuously throughout execution and feeds into monitoring and controlling processes.

Concept tested: PMBOK Direct and Manage Project Execution process outputs

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#project execution#change requests#deliverables#work performance

Community Discussion

No community discussion yet for this question.

Full GSLC Practice