GSLC · Question #437

You have been asked to create a project charter for a new database project. Management has stressed that in order to effectively create a project charter, you'll first need to understand all of the…

The correct answer is D. Quality improvement program your company uses. A project charter requires milestone schedules, measurable objectives, and a summary budget - but not details about the company's internal quality improvement program.

Security Program Management & Governance

Question

You have been asked to create a project charter for a new database project. Management has stressed that in order to effectively create a project charter, you'll first need to understand all of the following except for which one?

Options

  • ASummary milestone for the likely project phases
  • BMeasurable project objectives and related success criteria
  • CSummary budget
  • DQuality improvement program your company uses

How the community answered

(54 responses)
  • A
    7% (4)
  • B
    4% (2)
  • C
    2% (1)
  • D
    87% (47)

Why each option

A project charter requires milestone schedules, measurable objectives, and a summary budget - but not details about the company's internal quality improvement program.

ASummary milestone for the likely project phases

Summary milestones for likely project phases are a standard project charter component, providing a high-level schedule framework for the project.

BMeasurable project objectives and related success criteria

Measurable project objectives and related success criteria are essential charter components used to define what project success looks like.

CSummary budget

A summary budget is required in a project charter to establish the financial authorization and constraints for the project.

DQuality improvement program your company usesCorrect

A quality improvement program is an internal operational process, not a required input or component of a project charter. Project charters focus on authorizing the project and defining high-level scope, objectives, milestones, budget, and success criteria - not on how the organization manages its quality initiatives.

Concept tested: Project charter required components and inputs

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#project charter#project management#project objectives#milestone planning

Community Discussion

No community discussion yet for this question.