The correct answer is D. Quality improvement program your company uses. A project charter requires milestone schedules, measurable objectives, and a summary budget - but not details about the company's internal quality improvement program.
Question
You have been asked to create a project charter for a new database project. Management has stressed that in order to effectively create a project charter, you'll first need to understand all of the following except for which one?
Options
- ASummary milestone for the likely project phases
- BMeasurable project objectives and related success criteria
- CSummary budget
- DQuality improvement program your company uses
Explanation
A project charter requires milestone schedules, measurable objectives, and a summary budget - but not details about the company's internal quality improvement program.
Common mistakes.
- A. Summary milestones for likely project phases are a standard project charter component, providing a high-level schedule framework for the project.
- B. Measurable project objectives and related success criteria are essential charter components used to define what project success looks like.
- C. A summary budget is required in a project charter to establish the financial authorization and constraints for the project.
Concept tested. Project charter required components and inputs
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok