The correct answer is D. Quality improvement program your company uses. A project charter requires milestone schedules, measurable objectives, and a summary budget - but not details about the company's internal quality improvement program.

Question

You have been asked to create a project charter for a new database project. Management has stressed that in order to effectively create a project charter, you'll first need to understand all of the following except for which one?

Options

  • ASummary milestone for the likely project phases
  • BMeasurable project objectives and related success criteria
  • CSummary budget
  • DQuality improvement program your company uses

Explanation

A project charter requires milestone schedules, measurable objectives, and a summary budget - but not details about the company's internal quality improvement program.

Common mistakes.

  • A. Summary milestones for likely project phases are a standard project charter component, providing a high-level schedule framework for the project.
  • B. Measurable project objectives and related success criteria are essential charter components used to define what project success looks like.
  • C. A summary budget is required in a project charter to establish the financial authorization and constraints for the project.

Concept tested. Project charter required components and inputs

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok