GSLC · Question #42
Dawn is the project manager of the HQQ Project and she believes the project work is done. She has prepared the final project report, which includes information on the financial performance, schedule…
The correct answer is A. Project charter. The project charter authorizes the project at a high level and is not a scope completeness measurement tool; the scope statement, WBS, and WBS Dictionary are the documents used to verify and measure scope.
Question
Dawn is the project manager of the HQQ Project and she believes the project work is done. She has prepared the final project report, which includes information on the financial performance, schedule performance, and project team performance in the project. All of the following documents are used to measure the completeness of the project scope except for which one?
Options
- AProject charter
- BProject WBS Dictionary
- CProject scope statement
- DProject WBS
How the community answered
(53 responses)- A92% (49)
- B2% (1)
- C2% (1)
- D4% (2)
Why each option
The project charter authorizes the project at a high level and is not a scope completeness measurement tool; the scope statement, WBS, and WBS Dictionary are the documents used to verify and measure scope.
The project charter formally authorizes the project and appoints the project manager, but it contains only high-level goals and business justification rather than detailed deliverable descriptions needed to measure whether all scope has been completed; scope verification uses the scope baseline, which consists of the scope statement, WBS, and WBS Dictionary.
The WBS Dictionary provides detailed descriptions, acceptance criteria, and owner assignments for each work package, making it directly applicable to measuring scope completeness.
The project scope statement defines deliverables, exclusions, and acceptance criteria that serve as the baseline against which scope completion is measured.
The WBS decomposes all project deliverables into measurable work packages and is the primary structure used to confirm that every element of project scope has been addressed.
Concept tested: PMP scope verification baseline documents
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.