Janet is the project manager of the NHQ Project for her company. Janet is nearly done leading the project and there have been no cost or schedule overruns in the development of the new software for…

The correct answer is B. Gold plating. Gold plating occurs when a project team adds unrequested features or extras beyond the agreed scope, often consuming remaining budget without customer approval.

Security Program Management & Governance

Question

Janet is the project manager of the NHQ Project for her company. Janet is nearly done leading the project and there have been no cost or schedule overruns in the development of the new software for her company. The project team has been completing their work on time and there is still $75,000 left in the project budget. Janet decides to have the project team implement some extra features to the project scope to use all of the $75,000 in the budget even though the customer didn't specifically ask for the added features. This scenario is an example of which one of the following?

Options

  • AScope creep
  • BGold plating
  • CChange management
  • DValue added change

How the community answered

(48 responses)
  • A
    6% (3)
  • B
    90% (43)
  • C
    2% (1)
  • D
    2% (1)

Why each option

Gold plating occurs when a project team adds unrequested features or extras beyond the agreed scope, often consuming remaining budget without customer approval.

AScope creep

Scope creep refers to uncontrolled, gradual expansion of project scope - usually driven by stakeholder requests that bypass the formal change control process, not by a PM's unilateral decision to spend leftover budget.

BGold platingCorrect

Gold plating is the project management anti-pattern where the team voluntarily adds features, enhancements, or functionality that the customer never requested, typically justified by available budget or time. In this scenario Janet directs spending of $75,000 on unsolicited features, which is the textbook definition of gold plating. PMBOK discourages this practice because it introduces unvalidated scope, potential defects, and misaligned value delivery.

CChange management

Change management is the formal process used to evaluate, approve, and implement changes to project scope, schedule, or cost; Janet is not using any formal change process here.

DValue added change

Value added change is not a standard PMI or PMBOK term for this type of behavior, and adding unsolicited features does not inherently deliver verified customer value.

Concept tested: Gold plating in project scope management

Source: https://www.pmi.org/learning/library/scope-management-gold-plating-7141

Topics

#gold plating#scope management#project management#change control