Which of the following is a complete indexed set of records of the procurement process incorporated into the administrative closure process?

The correct answer is A. Contract file. In project management, the contract file is the formal, indexed procurement record compiled during administrative closure to document the full history of the procurement process.

Security Program Management & Governance

Question

Which of the following is a complete indexed set of records of the procurement process incorporated into the administrative closure process?

Options

  • AContract file
  • BRequired resources and skills
  • CRequired actions to complete the project scope
  • DDescription of the work packages

How the community answered

(62 responses)
  • A
    87% (54)
  • B
    2% (1)
  • C
    6% (4)
  • D
    5% (3)

Why each option

In project management, the contract file is the formal, indexed procurement record compiled during administrative closure to document the full history of the procurement process.

AContract fileCorrect

The contract file, as defined in the PMBOK Guide, is a complete indexed set of procurement records - including the signed contract, approved change requests, performance reports, and financial documents - that is incorporated into the administrative closure process to formally close out procurement activities and preserve a full audit trail.

BRequired resources and skills

Required resources and skills are inputs to resource planning processes such as activity resource estimating and have no role as indexed procurement records in the administrative closure process.

CRequired actions to complete the project scope

Required actions to complete the project scope belong to scope management and project execution planning, not to the procurement documentation set compiled during administrative closure.

DDescription of the work packages

Descriptions of work packages are outputs of Work Breakdown Structure (WBS) decomposition and describe deliverable-level scope; they are not part of the indexed procurement record maintained in the contract file.

Concept tested: Contract file definition in procurement administrative closure

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#contract file#procurement#administrative closure#project management

Community Discussion

No community discussion yet for this question.

Full GSLC Practice