The correct answer is B. Knowing the limits and the projects required helps determine the resources to purchase.. The scope statement documents project requirements and constraints, and understanding those boundaries directly determines what resources - such as equipment with mandatory compliance features - must be procured.
Question
Options
- AIt includes an introductory schedule management plan.
- BKnowing the limits and the projects required helps determine the resources to purchase.
- CIt is a deliverable-oriented collection of project components.
- DIt is the methods and procedures an organization must follow to create the activity list.
Explanation
The scope statement documents project requirements and constraints, and understanding those boundaries directly determines what resources - such as equipment with mandatory compliance features - must be procured.
Common mistakes.
- A. The scope statement does not contain a schedule management plan; scheduling artifacts are part of the project management plan, a separate document.
- C. A deliverable-oriented hierarchical decomposition of project work describes the Work Breakdown Structure (WBS), not the scope statement.
- D. The methods and procedures for creating an activity list are defined in the schedule management plan, not in the project scope statement.
Concept tested. Project scope statement defining requirements and resource constraints
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok